Willow Park (76008)
Baylor Scott & White Willow Park: what the state filing shows: a 19,000-square-foot small format hospital at 5400 E Interstate 20 Service Rd S, $15,000,000, completion filed for Dec. 21, 2026
5400 Willow Park Properties, LLC registered the hospital with the Texas Department of Licensing and Regulation on Jan. 6, 2026, with a construction start of Jan. 12, 2026 and a completion date of Dec. 21, 2026 as filed; the filing lists 8 inpatient beds and 8 emergency department beds and a current status of Review Complete.
Published Thursday, September 24, 2026, by The Aledo Ledger. Publisher: Christopher Weaver.
The state record. Project TABS2026009368, Baylor Scott & White - Willow Park, facility name Baylor Scott & White - Willow Park, was registered with TDLR's Architectural Barriers program on 1/6/2026. The filing lists the location as 5400 E Interstate 20 Service Rd S, Willow Park, TX 76008, in Parker County; new construction; 19,000 square feet; an estimated cost of $15,000,000; a start date of 1/12/2026 and a completion date of 12/21/2026; and a current status of Review Complete. The scope of work describes new construction of a 19,000 SF small format hospital comprised of 8 inpatient beds, 8 emergency department beds, CT & X-Ray imaging, and associated support spaces.
Who filed it. The owner of record is 5400 Willow Park Properties, LLC, 41 N. Jefferson Street, 4th Floor, Pensacola, Florida 32502; the tenant is EBD JV LLC; the design firm is HKS, Inc., 975 F St NW, Suite 200, Washington, D.C.; the registered accessibility specialist is Kimberly J. Goss, RAS #51, of Dallas. The filing says the project is privately funded, on private land for private use, and that the private funds are not provided by the tenant.
What the record does not show. A sales-tax permit at the address: the Comptroller's active permit list the Ledger read Sept. 24 does not show one at 5400 E Interstate 20 Service Rd S. A TDLR registration is the accessibility review required for construction of public buildings; it is not a building permit, a hospital license or an opening date, and the filed dates are the registrant's estimates. The Ledger will report an opening date when the company or the city posts one.
Sources: Texas Department of Licensing and Regulation, Architectural Barriers project TABS2026009368, Baylor Scott & White - Willow Park (registered Jan. 6, 2026), read Sept. 24, 2026; Texas Comptroller, Active Sales Tax Permit Holders (data.texas.gov dataset jrea-zgmq), read Sept. 24 (pipeline/fetch_new_businesses.py)
How this was sourced: Primary document: the TDLR project record, read Sept. 24, 2026. The Ledger did not review Baylor Scott & White's own announcements, Willow Park's site-plan or building-permit record, or any state hospital licensing record.