Aledo ISD 2023 bond program

Tracker; updated as the record changes

Where it stands. Lynn McKinney Elementary opened in August 2024 and the high school additions and renovations began in June 2024 under two guaranteed maximum prices; the safety and security project, 13 buses, playgrounds and bus parking were approved in May 2024; the district refunded bonds in May 2026.

Milestones

Every milestone links to the meeting report it comes from. The full thread of mentions is at /topics/aledo-isd-budget-bonds-and-tax-rate/. A tracker states facts from the record; it does not predict.